Construction

What to check when accepting work after construction or refurbishment

Signing the handover certificate is the moment when responsibility for the site passes to the client and the warranty period begins. Before signing, it is worth checking not only how the premises look, but also how they work and which documents are being handed over.

1. Finishes and building works

  • walls, ceilings and floors — cracks, unevenness, quality of paintwork;
  • doors and windows — opening, closing, seals, hardware;
  • joints, trims, silicone sealant in sanitary facilities;
  • falls and drainage — balconies, terraces, showers;
  • whether everything in the design and the contract has been done.

2. Building systems in operation

Systems have to be tested running, not just looked at:

  • ventilation — airflow in the rooms, noise, control panel;
  • heating and cooling — whether they reach the set temperature;
  • electrical — every socket and light, labelling of the distribution boards;
  • water supply and sewerage — pressure, leaks, drainage;
  • fire safety and security systems — test certificate from the installer.

3. Documents to ask for

  • as-built surveys and drawings (where everything runs in the walls and ceilings);
  • electrical installation test report (insulation resistance, earthing);
  • equipment data sheets, operating manuals and warranty cards;
  • system balancing and commissioning reports;
  • concealed works records;
  • a maintenance schedule for the first year of operation.

4. Snagging list

If the inspection finds defects, they are entered in a snagging list with a specific deadline for putting them right. The certificate can be signed with this list as an annex. It matters that each defect is described clearly enough that there is no later argument about whether it has been fixed — with the location, a photo and the expected result.

5. Warranty and ongoing maintenance

Make sure you know the date the warranty runs from, what it covers and how to report a warranty defect. For much equipment, the manufacturer's warranty is only valid if planned maintenance has been carried out — so you need to know the maintenance schedule on the day of handover.

Updated 03.10.2026 · ITTU

Frequently asked questions

Related pages: Commercial fit-out · Construction supervision · Technical maintenance of buildings

Can the certificate be signed if there are minor defects?

Yes, if the defects are entered in a snagging list with a deadline for remedying them, and the list is attached to the certificate. The contractor is then obliged to put them right.

Which documents should I receive after electrical work?

As-built drawings, distribution board schematics and the electrical installation test report with insulation resistance and earthing measurements.

When does the warranty start?

Usually from the date the handover certificate is signed, unless the contract says otherwise.

Need help with your site?

Describe the situation — we will reply and, if needed, offer a site visit.

You can attach drawings, photos or an equipment list. Required fields are marked with *.

Open the full request form
1. What do you need?
You can tick more than one service.
Construction
Building systems
Building services
2. Briefly about the site
Up to 5 files, 10 MB each. PDF, JPG, PNG, DWG.
When you send this request, your data is processed in accordance with our privacy information. No consent to marketing is required.

Thank you. Your request has been received.

Its reference number is —. We will get back to you using the contact details you provided.

A confirmation has been sent to the e-mail address given, if any. This confirmation does not mean a site visit has been agreed.

Request a quote